SOLAR & BATTERIES FOR YOUR BUSINESS: A BEGINNER’S GUIDE
Image credit: MC Electrical
By Finn Peacock
Chartered Electrical Engineer, ex-CSIRO & Founder of SolarQuotes®
Last Updated: 24th Nov 2026
This guide is for you if you are considering investing in a commercial solar & battery system for your business in Australia.
Many commercial solar systems pay for themselves within five years.
Solar is a great fit for businesses that use most of their electricity between 9am and 5pm. Battery prices are dropping, and you can claim the federal battery rebate, so it’s worth thinking about adding a battery too.
A good commercial solar system costs about $700 to $1,200 per kW installed after the solar rebate. Since 1 October 2026, the rebate now covers systems up to 1 MW, instead of just 100 kW.
If you’re new to solar, our residential solar 101 guide explains the basics in about 10 minutes. Ready to see prices? You can get commercial solar quotes from trusted, pre-vetted Australian installers.
Otherwise, here are some key things to know before you get quotes for solar & batteries for your business:
- The Three Distinct Size Breaks For Commercial Solar Systems.
- Issues With Connecting Larger Systems To The Grid
- Typical Costs And Paybacks
- Monitoring And Maintenance
- The “Commercial Solar Rebate”, AKA STC’s Versus LGC’s
- Why Commercial Solar Systems Don’t Always Need A Roof
- Financing A Commercial Solar Power System
- What To Expect From Your Initial Installer Visit/Consultation
- The Importance Of IRR And Discount Cashflow Analysis As Part Of Your Quote
- The Difference Between Commercial-sized Solar Panels And Residential-sized Solar Panels
- Inverters In A Commercial-sized Solar Power System
- Commercial Solar Contracts, And When Australian Consumer Law Applies To Commercial Solar
- Batteries – Are They Worth It?
#1 The Three Distinct Size Breaks For Commercial-sized Systems
To put commercial-sized solar systems into perspective, the average home solar system installed in Australia is now just over 10 kW.
Less Than 30 kW (Up To About 70 Panels)
These systems use the same hardware and follow the same grid connection rules as residential systems. So, installers who work on residential systems can usually handle business installations up to this size without needing special commercial solar expertise.
A 30 kW system will generate about 120 kWh of electricity a day on average over a year. At around 28c per kilowatt-hours (kWh), that saves approximately $1,000 per month if 100% self-consumed (which is possible in commercial situations).
30-100 kW
Commercial solar arrays of this size need special systems to protect the grid from the electricity they generate, and you’ll need permission from your local electricity network to connect. It’s best to use a commercial solar specialist for systems this size or bigger.
Commercial solar systems in this size range are typically installed on medium-sized office buildings, local clubs, and small retail businesses.
100 kW – 1 MW
From 1 October 2026, systems in this range can also claim the upfront STC rebate (covered in more detail in point #5 below). They come with some extra paperwork, including a structural engineering report and a single-line diagram of the system. They no longer need a special meter and annual reporting to claim their rebate.
These are typically installed in hotels, large offices, wineries, and small- to medium-sized factories.
These systems are very large, so we recommend using a specialist installer who understands the engineering needs of big commercial systems. For systems above 1 MW, you claim LGCs instead of STCs. If you want a referral, feel free to contact us.
#2 Connecting Large Commercial Solar Power Systems To The Grid
When installing systems of 30 kW or more in Australia, it is very important to have the network’s written approval for the system. Every solar power system connected to the grid must be approved.
For larger commercial systems, most (if not all) approvals are issued with conditions. For example, “This 55 kW system has been approved, subject to the system having an export limiting device set to 10 kW”.
It’s very important to know about these conditions. Meeting them can mean extra costs and equipment, and exporting your system might reduce your expected savings.
Some less reputable commercial solar installers might not tell you about this, since they may not have included it in their original costs.
They may think that if they raise their quote for extra network compliance work, they could lose your business. If they ignore it and go ahead, they might hope the network or its associates won’t inspect the system.
That’s why you should get a formal copy of the approval and, if you can, ask an independent consultant for their opinion. Investing in a large commercial solar panel array is a big commitment, so it’s best to avoid any unpleasant surprises.
If you’re adding a battery, tell your installer up front. Battery inverters usually count toward the capacity your network approves.
You might also need council approval. Most rooftop solar doesn’t need planning approval, but heritage listings, ground mounts, and tilt frames can all require it.
Make sure to discuss this with your solar company and check with your local council. Most good commercial solar companies have an architect and private certifier to help speed up approvals.
#3 Typical Solar Costs And Paybacks
Good-quality commercial solar power, over 30 kW and up to 100 kW, will cost around $700-$1,200 per kW installed in Australia as a ballpark figure after the solar rebate is applied. Using microinverters or power optimisers will add around 15-20% to the overall final cost, compared to using a string (or central) inverter system.
Systems under 30 kW need less network protection and associated engineering, while bigger systems benefit from economies of scale. For systems between 100 kW and 1 MW, prices vary too much from site to site to provide a reliable ballpark figure. Please get multiple quotes.
Plan for extra costs that might not show up in the first quote. These can include a structural engineering report, switchboard upgrades, and for systems 30 kW and above, network connection work and export-limiting equipment.
An important point to note is that some commercial premises have signed long-term tariff contracts with their electricity retailer. This will affect future paybacks and savings from going solar. You need to dig up the terms you agreed to and understand them. Of particular importance is when your contract will expire and the projected increase in tariff charges.
While you’re reading that contract, check two more things:
- Does it require your retailer’s consent before you install solar?
- What does it pay for solar you export?
Be persistent when following up, as you might get passed between departments. Many commercial solar companies can explain how installing solar panels will affect your tariff.
For businesses, electricity bills tend to reflect low “raw consumption” costs. Most of the cost is in other fees and charges, and you need to confirm which of them installing solar will reduce or offset. For many businesses, one of the biggest is the demand charge. Solar often doesn’t touch it, but a battery can.
Do your own research to make sure the sales pitch matches reality. You might be surprised!
To summarise:
- A good commercial solar system in Australia costs about $700 to $1,200 per kW installed after the rebate. Many commercial solar systems pay for themselves within five years.
- Verify your contract duration with your energy retailer, and whether you need its consent to install solar.
- Confirm what charges on the bill will be reduced when solar panels are installed, and by how much.
- Check what the companies quoting you say about these points, and always do your own research!
#4 Monitoring And Maintenance
Don’t buy a commercial solar & battery system unless it monitors both solar energy generation and electricity use. Without both, you won’t have the info you need to keep your bills as low as possible after installing solar.
It’s smart to have someone in your business keep an eye on the system’s weekly generation.
In the Australian commercial solar space, it is not uncommon to see a business that has only been sold simple generation monitoring (the cheap salesman’s version of “monitoring”). The business believes the building is consuming a fair bit of the generation it can see, convinced by the cowboy salesman who “analysed their load profile”.
The salesman’s logic is “Well, the system will generate 200 kWh per day conservatively; your consumption is approximately 150 kWh during the day, meaning that this would be more than enough to cover most of your loads”.
Without consumption data, you can’t verify that claim. If your solar isn’t used when it’s generated, it gets exported for little or no value, and you won’t see the bill reductions you expected.
Any good monitoring solution will let you check your gross consumption, so you can view the ‘before and after’ of solar’s contribution to your business for any particular hour. If you add a battery, make sure the monitoring shows what it’s doing too. One brand of monitoring software that we can recommend is Solar Analytics.
It’s important to have a maintenance schedule. Installers accredited by Solar Accreditation Australia must give you one. For larger commercial systems, installers will offer a detailed, custom schedule, either to do themselves or for you to arrange with a third party.
Usually, an installer will check your system every six months for the first two years. They often have a preferred pressure-washing company to recommend if dirt or debris starts to affect performance.
Clean your panels as needed, rather than on a set schedule. Solar panels usually clean themselves, but in high-pollution or dusty areas, they might need manual cleaning.
Note: Some installers may try not to honour a warranty if a third party does the maintenance. This is just a sneaky way for them to make more money. Avoid these companies.
#5 The “Commercial Solar Rebate” – AKA STCs Versus LGCs
Commercial solar systems up to 1 MW are eligible for Australia’s solar rebate, worth around $250 per kW installed in Sydney, Brisbane, Adelaide, or Perth (in Melbourne and Hobart, they’re worth a little less because those areas receive less sunlight). That’s about $62,000 off a 250 kW system.
Until 1 October 2026, the cut-off was 100 kW. The government expanded the scheme to cover systems up to 1 MW, so far more medium-sized businesses, farms, and community organisations now get an upfront discount.
The rebate works through Small-scale Technology Certificates (STCs). A simple explanation is that you are paid upfront for the electricity your system is expected to generate over a set period, known as the deeming period. The value varies according to market conditions and installation location.
This rebate is almost always applied as a point-of-sale discount on a commercial solar quote, and for the first 100 kW it drops in value every year. Say your business was quoted $30,000 for a 30 kW system in Sydney, Brisbane, or Adelaide. A 2026 install includes an STC discount of about $7,450, while a 2027 install only gets $5,940.
Use our STC calculator to check the figure for your postcode and system size. It now covers systems up to 1,000 kW.
Why Stopping At 99.9 kW No Longer Makes Sense
For systems up to 100 kW, the rebate shrinks every 1 January as the scheme counts down to its end in 2030. Systems installed in 2026 get 5 years’ worth of certificates; those installed in 2027 get 4, and so on.
Systems between 100 kW and 1 MW get a fixed 5-year term, all the way to 2030.
Who Qualifies For The Rebate On 100 kW-1 MW Systems?
To claim STCs, a system between 100 kW and 1 MW must:
- Be commissioned on or after 1 October 2026, as indicated by the testing and commissioning date on the electrical compliance certificate.
- Use components on the Clean Energy Council’s approved list, installed by an installer accredited by Solar Accreditation Australia.
- Have a network connection agreement and any planning approvals it needs.
- Come with a structural engineering report, a single-line diagram of the system and geotagged photos of the installer at commissioning.
STCs must be created within 12 months of installation, so make sure your installer lodges the claim promptly.
The 1 MW cap counts all related solar on the site, so you can’t get around it by building in stages. If you’re expanding an existing system, only the new capacity earns STCs, and the combined system must land between 100 kW and 1 MW. Ask your installer to confirm your site’s total solar capacity in writing. Our mid-scale solar rebate explainer and the Clean Energy Regulator cover the fine print.
STCs Or REGO Certificates?
You can’t claim STCs and ongoing certificates for the same solar capacity. If you take STCs on a 100 kW-1 MW system, you can’t create Renewable Electricity Guarantee of Origin (REGO) certificates for its 5-year deeming period.
If your business needs certificates to back up renewable energy claims in its emissions reporting, talk to your accountant before you choose.
Systems Over 1 MW
Once your system is more than 1 MW, you are no longer eligible to claim STCs, and must instead claim Large-scale Generation Certificates (LGCs).
The key difference is that the STC rebate is paid in advance and essentially works as an upfront discount on the cost of a system. LGCs must be accurately tracked, reported, and claimed each year.
To claim LGCs, you first need to register your business as an “accredited power station” with the Clean Energy Regulator. Your solar installer will help you with this process. They then need to ensure that your metering meets National Electricity Market standards, so you can properly track your generation.
Ultimately, this means systems over 1 MW don’t attract an upfront discount. That’s an important consideration when calculating the rate of return and the cash flow impact on your business.
Be aware that LGCs are now worth far less than they used to be. The LGC scheme ends in 2030, and the REGO scheme, which started in November 2025, is taking over that role.
State Incentives
Some states add their own incentives on top of the federal rebate. Victoria, for example, offers a discount on commercial solar systems between 30 kW and 200 kW through its Victorian Energy Upgrades program. Businesses may also be able to claim federal STCs on the same system. Check what’s available with your state energy department, and ask your installer whether incentives can be combined.
#6 Commercial Solar Designs And Layouts – Or Why Commercial Solar Doesn’t Always Require A Roof
Weight is one of the biggest factors in installing a commercial-sized solar array on a business’s roof.
It is vitally important that a structural engineering certificate is produced and that an engineer has physically inspected the site. If your system is between 100 kW and 1 MW, you’ll need an as-built structural engineering report to claim the solar rebate anyway.
Be sure that a detailed roof plan is shown to you well before installation.
Flat-panel arrays are more common than tilt-frame installations. They’re cost-effective, since tilt frames add extra cost, and can be easily changed if you need to make last-minute adjustments.
Ground-mount systems are an option if your roof isn’t suitable for solar, but they’re less common and need much more planning and cost than roof-mounted systems.
#7 Financing A Commercial Solar System
There are four main ways commercial systems can be financed in Australia, and all of them work for batteries as well as solar:
1) Cash/CapEx
Technically not finance, but still a common way to purchase a system.
Paying cash for a commercial solar system is always the cheapest option and gives you the fastest payback, since finance or leasing adds extra fees and charges.
The downside is that large commercial solar systems are a big expense, and you might want to use that money elsewhere in your business.
2) Power Purchasing Agreement (PPA)
PPAs are a type of solar leasing arrangement.
The core idea is that a third-party retailer installs a commercial system on your property and legally owns it, so it’s obligated to maintain it. It then enters into an agreement with your business to supply you with a set amount of electricity over a long-term period.
The main benefits are no upfront cost to install the system, and your business electricity costs are usually lower overall because PPA electricity is typically cheaper than what you pay your retailer now.
The downside is that your business has to buy all the electricity the system generates, whether you use it or it’s sent to the grid for a feed-in tariff.
Self-consumed solar energy is far more valuable than solar electricity exported to the grid for a feed-in tariff. So if you are considering a PPA, it is very important to have the system optimally sized for maximum self-consumption.
PPAs set out the price of solar energy for the duration of the agreement. While a low price for year one is obviously a good start, it’s very important to read the fine print on how the prices will be adjusted over time.
The best PPA is one where prices go up slowly over time, or not at all. That’s better than a low starting price that jumps by 5% each year.
3) Loan
A business or green loan lets you negotiate with a commercial solar installer like a cash buyer. The savings from your new solar system might be more than the loan interest, making it an easy way to avoid a big upfront payment.
4) Building Upgrade Finance (SA, VIC and NSW only)
Building Upgrade Finance (called Environmental Upgrade Finance in Victoria) helps building owners borrow to improve the energy, water and environmental efficiency of existing commercial buildings, with repayments collected through council rates.
It helps solve problems like getting access to capital. It also helps when building owners pay for upgrades but tenants get the benefits, like lower electricity bills.
Not every council offers it, so check with your council or state government for details about eligibility.
A Word On Tax
Ask your accountant how depreciation works for your system. The $20,000 instant asset write-off for small businesses is now permanent, but most commercial systems cost more than that.
#8 What To Expect From Your Initial Installer Visit/Consultation
Any good Australian commercial solar installer will do an energy profile analysis on your property.
The main things they will look for are:
- The billing structure: what kind of tariff is your business on?
- The charges that cannot be avoided: ancillary charges, Australian Energy Market Operator (AEMO) charges, service availability charges and so on.
- The energy consumption during daylight hours, especially in winter. This shows them what matters more: your roof space, or what you, as the customer, actually need. For example, you may need a 100 kW system but can only fit 50 kW on your roof. An energy profile analysis will tell you definitively whether it’s still worth going ahead.
- Whether a battery suits your load profile, especially if you pay demand charges.
The visit should also include:
- A site visit or inspection.
- Understanding your business needs and goals.
- Analysis of power bills and interval data, to accurately project paybacks.
#9 The Importance Of IRR And Discount Cashflow Analysis As Part Of Your Quote
Internal Rate of Return (IRR) is a better metric than Return On Investment (ROI), because the capital invested in a solar power system is essentially gone after its 25-year lifetime.
Good commercial solar installers should include a detailed cash flow model with their quote. Since this comes from a salesperson, it’s smart to have your accountant check it.
It’s very rare for even dodgy operators to put false numbers in an analysis. Numbers don’t lie, and even the worst salesperson knows that making up numbers can backfire. The real issue is in the assumptions. PPAs and leases use different assumptions about future interest rates and electricity prices, and these affect the calculations you see.
#10 The Difference Between Commercial-sized Solar Panels And Residential-sized Solar Panels
Residential roofs are generally much more restricted in usable space than, say, a factory roof, so residential-sized solar panels are typically smaller, lower-wattage panels.
Commercial roofs usually have plenty of space, so larger, more powerful panels are used, often 600 W or more. This means you need fewer panels overall, which lowers installation costs.
#11 Inverters In A Commercial-sized Solar System
Broadly speaking, there are three options when it comes to choosing a solar inverter setup for a commercial-scale job:
- Microinverters or optimisers
- Chained string inverters
- Large central inverters
Cost is important in a commercial system. Microinverters and optimisers usually cost 15-20% more than regular string inverters, but they offer extra safety and performance benefits.
For commercial-scale installations in Australia, it’s often hard to justify spending an extra $50,000 on microinverters when a string inverter system will produce almost the same amount of power.
String inverters are usually more cost-effective. In our experience, most commercial installers prefer to chain several string inverters together instead of using one large central inverter.
This industry preference is for a variety of reasons:
- Design flexibility. Few commercial roofs suit a large single array, and multiple smaller inverters offer design flexibility through different strings and Maximum Power Point Trackers (MPPTs).
- Access. It’s much easier to move and install several smaller inverters than a central inverter the size of a small room, especially if you need heavy machinery to lift and position it.
- Redundancy. One failure doesn’t cripple the entire system.
If you’re planning a battery now or later, ask about a hybrid inverter, which can run solar and a battery together.
In the end, your solar installer should recommend what’s best for your situation, and you can decide if you want a simple system or something more advanced.
#12 Commercial Solar Contracts, And When Australian Consumer Law Applies To Commercial Solar.
Australian Consumer Law gives consumers an arsenal of legal protection and recourse (whether they’re aware of it or not) against shonky solar installations. But it normally applies only to goods and services costing $100,000 or less, including GST.
Many smaller commercial systems will fall under this threshold. But now that systems up to 1 MW can claim STCs, plenty of rebate-eligible systems will cost well over $100,000 and won’t be covered.
Larger systems would, presumably (we are not lawyers!), fall under general contract law instead.
This means it’s extremely important that you understand the contract you’re signing, and that both parties are clear on their responsibilities.
The bottom line is that commercial solar systems are a big investment for your business. It’s a good idea to have a lawyer review any contracts before you sign.
#13 Batteries – Are They Worth It?
A battery can save your business thousands of dollars a year on power bills.
Batteries make the most sense for businesses that:
- Pay high demand charges that a battery will reliably reduce.
- Export a lot of solar for little or nothing, because a battery can store it for use later in the day.
- Need to back up vital loads for blackout protection.
Demand charges are based on your highest burst of usage over a period, not just your total energy use. In South Australia, for example, SA Power Networks charges larger businesses based on their highest average demand between 5pm and 9pm on summer days. Solar can’t help much at that time since the sun is down, but a battery can.
If backup power is important for your business, plan for a dedicated critical-loads switchboard during the design stage, instead of trying to back up the whole site.
The Federal Battery Rebate For Businesses
Small businesses and community facilities can claim the federal battery rebate, not just households. It cuts roughly 25% off the cost of a modest-sized battery and is applied as an upfront discount, like the solar rebate.
The battery must be between 5 kWh and 100 kWh. It must also be able to join a Virtual Power Plant (VPP), though you don’t have to join one.
The catch for businesses is the size cap. Only the first 50 kWh of usable capacity is subject to the rebate, so a 200 kWh commercial battery gets no more than a 50 kWh one.
This means the federal rebate mainly helps smaller businesses whose battery needs are more like a large household’s than a factory’s.
The rebate steps every six months. Use our battery rebate calculator for the current figure.
New South Wales Business Battery Incentive
In New South Wales, businesses can also receive an upfront discount on batteries ranging from 20 kWh to 30 MWh through the state’s Peak Demand Reduction Scheme, which started on 1 September 2026. It’s a much better fit for larger commercial batteries than the federal rebate. The NSW Government says it can be combined with the federal solar rebate.
When A Battery Doesn’t Make Sense
Batteries still aren’t worth it for every business. If you don’t pay demand charges, don’t export much solar, and don’t need backup power, it’s usually better to invest in a larger solar array first.
Either way, ask for a battery quote alongside your solar quote. Our guides to battery cost and battery payback go into the numbers in more detail.
The Next Step
That’s my ‘101’ guide to solar & batteries for your business. With this information, you’re now ready to get commercial solar quotes for solar, a battery, or both.
If you’re considering installing solar & batteries for your business, SolarQuotes® can help you get quotes from high-quality, pre-vetted Australian installers quickly and easily: